Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2376

.pdf
Скачиваний:
4
Добавлен:
07.01.2021
Размер:
6.68 Mб
Скачать

ment of water and debris. To totally

arch ribs, bracing, and floor - was veri-

close the ends of the tubular shapes,

fied by wind tunnel tests.

horseshoe-shaped plates were welded

Erection

to the ends of the tubes.

At the portals, the K-bracing was ter-

 

minated with a three-dimensional X-

Erection of the bridge was accom-

shaped connection. The multi-jointed,

plished using temporary towers resting

three-dimensional intersection of the

on the arch footings and a system of

bracing was achieved by welding

bridge strand backstays and forestays.

plates into an octagon and welding the

Hydraulic jacks in the stays allowed

ends of the tubes to the sides of the oc-

alignment adjustments to be made dur-

tagon. More than 760 m of fillet welds

ing erection.

were used to make up the bracing.

The erection progressed by lifting and

Another part of the bracing system is a

bolting successive 15.2 m long welded

2.1 m square welded box strut between

steel rib sections into place with a

arch ribs directly below the roadway at

barge-mounted crane floating on the

each end of the bridge. Access to the

lake. As adjacent rib sections were

interior of the ribs is through lockable

placed, the welded tubular K-bracing

doors in these boxes. Electrical distrib-

was installed to maintain alignment

ution centers are also inside the struts.

and rigidity of the ribs. Shop fabrica-

The floor system for the 11.5 m wide

tion accuracy was maintained so well

roadway

consists

of longitudinal

that there were no mismatches during

stringers, supported on welded I-girder

erection.

floor beams. Floor beams are spaced at

Owner:

15.2 m centers and are hung from the

arch ribs with eight wire ropes, four at

Arizona Dept of Transportation

each end of a floor beam. Welded steel

Engineers:

girders 2.0 m deep are used as exterior

HNTB Corp., Kansas City, MO

stringers and also function as stiffening

Main contractor:

girders

for aerodynamic ''stability.

Edward Kraemer & Sons, Inc., Plain,

About 2.1 m of fillet welds were re-

WI

quired to fabricate the floor system.

Service date: 1990

The overall stiffness of the system -

BRIDGE SCOUR FAILURES

Introduction

D.V. Mallick M.M.Tawil

 

Technical Advisors

 

Failure of a bridge is viewed seriously

National

Consulting

Bureau, Tripoli,

by the public since it involves not only

Libya

 

 

traffic disruption and the loss of tax

 

 

 

payer's money but can also result in

203

loss of human lives. It reflects on the

covered by load or safety factors are

reliability of the design procedures as

revealed in weaknesses after construc-

well as on the quality of construction.

tion. Geotechnical investigations are

Use of poor construction materials and

very important for the design of bridge

inadequate design

assumptions are

foundations.

generally this suspects. Designers and

This paper describes a case history of

contractors have to be extra cautious

failure of three reinforced concrete

while designing

and constructing

(RC) highway bridges built across

bridges to resist the effects of natural

Wadi El Nagah watercourse in the

hazards like floods, earthquakes and

northeastern part of Libya. Two out of

landslides in addition to normal traffic

three bridges collapsed and one suf-

loads. Studies have been made in re-

fered damage that could be repaired.

cent years to understand the pattern of

All these bridges have been victim of

occurrence, of these natural phenome-

heavy floods in the wadi, which caused

na statistically, attempting to compute

severe damage due to scour, erosion

probability of their future occurrence.

and undermining of the soil below the

The cumulative effect of various as-

foundations of intermediate piers and

sumptions and approximations intro-

the abutments. In all cases, parts of the

duced at the analysis and design stage

approach road embankments were also

of a bridge which are not sufficiently

washed away.

Fig. 38

204

Description of the Bridges

The location of three bridges built across Wadi El Nagah are shown in Fig. 38. The catchment area of the wadi across which these bridges were built consists of hilly terrain. Mean annual rainfall precipitation in this region is around 400-600 mm. Almost all the precipitation occurs during the winter months, from October to January of each year.

Bridge A, built about three decades ago, consisted of three simply supported spans of pre-stressed reinforced concrete beams supported on two central piers and two end RC abutments. The foundation of all these supporting elements consisted of shallow block foundations. Bridge B was a bowstring girder RC bridge supported on two massive intermediate plain concrete pillars and anchored at both ends to earth fill embankments. Bridge C, part of the new coastal highway, consisted of an RC portal frame with propped overhangs. Vertical supporting members of the portal are shear wall type piers 10 m high and 0.7 m X 6.0 m in cross section. The foundations of these piers consisted of RC blocks 10 mX 5 mX 1.5 m resting on plain concrete mats of 300 mm depth and located 4 m below the planned wadi bed level. The RC abutments of this bridge were embedded in the approach road embankments at both ends. Gabion protection was provided as per the design.

Damage Assessment

Bridge A was badly damaged by the flood water. One abutment collapsed

and the beams at that end of the span were twisted. Foundation blocks of the intermediate piers were exposed. Part of foundation soil of the far end abutment eroded away, leaving the foundation block partially suspended. Expansion joints between the concrete deck sections over the intermediate supports widened considerably due to distortion and the lateral displacement of the bridge decks.

The old multispan RC bowstring girder Bridge B totally collapsed. Its two intermediate plain concrete supporting piers overturned sideways along with the foundation blocks and moved downstream to Bridge C.

The new Bridge C did not suffer any appreciable structural damage although scouring of the wadi bed, accompanied by undermining of the soil below the foundation blocks of the vertical piers and the east RC abutment did occur, leaving them partially suspended (Fig. 3). The approach connection to the bridge deck from the east was destroyed due to the collapse of the approach concrete slab caused by erosion of the earth fill at the back of the abutment. This bridge has been repaired and opened to traffic.

Causes of Damage

Scour of the wadi bed, undermining the soil below the intermediate piers and the abutments' foundation blocks, and the erosion of the approach road embankments during a heavy flood, were the causes of the damage and collapse of these bridges. This is not the first time such damage has occurred.

205

"Bridges are vulnerable to natural hazards ranging from hurricanes to earthquakes. But scour is the problem that has caused more bridges to Mil than all of rest combined. One study... concluded that among 86 bridge failures [in the USA] from 1961 to 1976, 48 were due to floods. Out of 48, 46 were due to bridge scour" [1]. Another recent survey revealed 494 of the 823 bridge failures in the USA from 1951 to 1988 were primarily the result of scour of foundation material [2].

In addition, some other circumstances aggravated the damage and led to collapse of one of these bridges. The damages occurred partly due to shortcomings of the design and partly due to ignorance of the effects of a temporary road embankment across the wadi about 500 m upstream from Bridge A [3]. This temporary road embankment acted like an earthfill dam across the wadi, creating an artificial lake upstream. Due to heavy floods, this dam' gave way, releasing a flood with a fast moving flow of water about 12 m high, as observed from the water marks on the soffit of the deck of Bridge C, resulting in erosion and undermining scour of the wadi bed and the side embankments. The damage to Bridge A was severe due to its undesirable location at a bend in the wadi, as shown in

Fig. 38.

Rehabilitation

Two of the three bridges on Wadi Al Nagah were abandoned and the third, Bridge C, has been rehabilitated. The main problems in rehabilitating Bridge

C were to support the foundation blocks of one intermediate pier and one abutment, and to provide a new reinforced concrete approach road slab.

The repair work had to be planned very carefully in order not to disturb the structural safety of the other parts. of the bridge. The sequence of the repair work consisted of removing loose and eroded soil from below one side of the foundation block at a time, thorough compaction of the base and measuring any deflection of the suspended part of the foundation block. This part was then block concreted.

Similarly, the other side of the pier was prepared and block concreted.

To ensure proper contact between old and the new concrete blocks, epoxy mortar was injected between them. Then the central part below the foundation block was cleared of all soil deposits. Precast concrete beams were inserted on the prepared base. Finally, the end sections were grouted, thus providing another foundation slab to the existing foundation block. A similar procedure was adopted for the repair of the abutment foundation. The depth of the new foundation system was based on scour depth calculations. After carrying out all necessary repairs for rehabilitation, the wadi bed and approach road embankment slopes were suitably protected. This bridge has now been operational for two years. The owner was advised to dismantle Bridge A, so as to provide a clear path for the wadi stream approaching Bridge C. To date, this damaged bridge has not been removed.

206

Lessons

 

 

- Location of a bridge near a bend in a

 

 

 

 

 

stream should be avoided.

 

- Bridge planning and design is not

-

There is a need for research to es-

only a job of structural engineer, but is

tablish

the

relationship

between

the joint responsibility of a team of

flow depth, flow velocity and total

structural, hydrology and geotechnical

scour depth for actual conditions in the

engineers. Structurally well

designed

field.

 

 

 

 

bridges have failed as a result of hy-

References

 

 

 

draulic conditions, primarily due to

 

 

 

scour of foundation material.

 

[1] MURILLO, J. A. The Scourge of

-

The uncertainty of collecting proper

hydrological data, the probability of

Scour. ASCE Civil Engineering, July

occurrence of future severe storms and

1987, pp. 66-69.

 

 

their effect on the bridge system re-

[2] HUBER, F. Update: Bridge Scour.

quire

advance

preparation for all

ASCE

Civil

Engineering,

September

eventualities.

 

 

1991, pp 62-63.

 

 

-

Initial evaluation of scour vulnera-

[3]

MALLICK,D.V.;

ELWAFATHI,

bility of streambed material is es-

A.M.

 

 

 

 

sential. Due to the stochastic nature of

Damage Study of Three Reinforced

the

hydraulic parameters

involved

Concrete Bridges over Wadi El Nagah,

in bridge design, appropriate scour

Libya. Conference on Our World in

countermeasure programmes, like in-

Concrete & Structures, Vol. VI

stalling riprap, guide banks to protect

(1987),

Singapore, 25-26 August

abutments and

embankments and

1987, pp 50-66.

 

 

sheet piling along the face of piers

 

 

 

 

 

 

and/or abutments, must be clearly

 

 

 

 

 

 

planned in advance.

 

 

 

 

 

 

 

A NEW FOOTBRIDGE, AUSTRIA

 

 

 

 

 

 

 

 

 

 

 

Graz. Austria, have an elevation dif-

Harald Egger,

 

 

ference of about 2.2 m. The designers

Prof. Dr Hermann Beck, Research As-

felt that a simple straight beam in-

sist.

 

 

 

clined across the river at this point

Univ. of Technology Graz, Graz, Aus-

would

be aesthetically

unsatisfactory.

tria

 

 

 

They therefore opted for spanning the

Design

 

 

river with a beam that was slightly ele-

 

 

vated at its centre and horizontally

 

 

 

 

 

supported by columns, with its upper

At the site selected for a new foot-

surface serving as a footpath.

bridge, the banks of the Mur River in

 

 

 

 

 

 

207

Fig. 39

footpath divides "before leading down to the left and right. The aim of designing a fine-membered bearing structure led to the development of a compound beam construction comprising a stiffening member, with a tensioning member and a compression member on the underside of the bridge (Fig. 39).

The height and width of the stiffening member decrease toward the centre of the bridge from the supports at either end, i.e., toward the compression member. The shape of the composite prismatoid thus also determined the spread of the tensioning member underneath toward its supports.

In accordance with the geometry and design principle of the entire construction, the bridge deck has been designed as a folded plate structure forming an integral part of the bearing system. On one bank the deck rests upon the body of the, stiffening member; on the other bank it extends from the stiffening member's sides.

The bearing structure of the bridge rests on two pairs of columns on the banks of the river, cantilevering on either side. On the right bank it extends to the old non-bearing embankment wall, while on the left-hand bank the body of the stiffening member ends in a cantilever design, with the walking deck extended from it to permit direct access to the footpath without ramps or stairs.

Construction

The stiffening member of the bridge covers an effective span of 55.8 m. Its cross section has a height of 2.0 m over the columns and 0.7 m at the Centre. The bridge deck, a hollow steel plate, is folded on its lower side and forms part of the stiffening member. The deck is connected asymmetrically to the trilateral body of the stiffening member in relation to the centre of the bridge. On the left side of the bridge its

208

top follows the top edge of the stiffening member; on the right side, starting from the centre of the bridge, it intersects with the lateral surfaces of the prismatoid, parallel to its bottom edges. The compound stiffening member is also asymmetrical. Its characteristic cross section is shown in Fig. 40.

Fig. 40

The walls of the trilateral prismatoid are 15 mm thick over its entire length, but its longitudinal braces - an additional flange plate welded where the bridge deck begins to descend - were adapted to the asymmetry of the stiffening member, as was the quality of the plate used. The trilateral prismatoid is reinforced by transverse bulkheads placed 2.2 m from each other, corresponding to the folds of the cover plate of die bridge deck. The entire structure is sealed airtight. All parts, whether assembled in the shop and at the site, were joined by welding.

In order to make sufficient allowance for floodwaters, the tensioning member underneath the bridge has a very flat design, with the elements spreading out from the centre to the supports, where they are eccentrically connected

to the stiffening member. This spreading is a consequence of the geometrical configuration of the bearing structure and design considerations. Stability of the stiffening member is also improved by this expansion and by the eccentric connections, the latter also reducing deflection of the stiffening member.

To achieve the required stiffness for the entire compound bearing structure, 145 mm thick bands of grade Fe 510 steel were used for the tensioning member. These relatively heavy bands were attached to the stiffening member at the quarter points of the central bridge span and supported against wind loads. The connection of the tensioning bands to the compression member shown in Fig. 41, which illustrates both the solution originally required by the invitation to tender and the final method employed by the contractor. Behind the supports, the bands were anchored to angle cleats that were laterally welded to the sleeve plates of the stiffening member. The steel bands were stretched in place, but not prestressed.

The stiffening member rests on four slender free-standing columns. It is fixed to one column, and longitudinally movable but transversally fixed to the other three so that all four columns may contribute to the transmission of wind loads. In addition, the entire bearing structure resting on the columns is protected against transverse wind attack from below.

For reasons of time and cost, the bearing structure of the bridge, which put heavy demands on manufacturing skills, was produced at the plant. It was

209

manufactured in large sections which were then transported by road to the site, in part with the bridge deck already attached to the bearing structure.

Fig. 41

on the river's banks, and hoisted into position by an automobile crane. Erection was accomplished in three nightshifts. The sections were placed on a temporary support and the entire bearing structure was then joined together by welding. After a final insertion of the tensioning member on the underside of the bridge, the auxiliary support was removed.

Architects:

G.Domenig and H. Eisenköck, Graz, assisted by G. Wallner

Civil Engineers:

H.Egger, Graz, assisted by H. Beck

Contractors:

Alpine Bau (concrete), Salzburg Vöest-Alpine (steel), Linz

Service date: 1993

These sections were assembled into larger units, whenever possible directly

IS ISO 9001 EFFECTIVE FOR ENGINEERING CONSULTANCIES?

Jørgen Laustsen, Civil Eng. Copenha-

on a large scale - but mostly for the

gen, Denmark

sake of marketing.

 

Attitudes towards ISO 9001 among

The quality assurance processes de-

English, German and Danish consult-

scribed in ISO 9001 have not been

ing engineers were the subject of a re-

greeted with unanimous enthusiasm by

cent research study [1]. The study is

consulting engineers. Consultants in

based on interviews with twenty-nine

England, Germany and Denmark have

consulting engineering companies and

in fact responded quite differently to

institutions. Thirty-five additional

the ISO 9001 quality assurance stan-

companies responded to questionnaires

dard. Danish engineers have generally

on the subject.

declined to adopt the standard, the

Criticism in Denmark

Germans are decidedly more keen on

their own DIN standards, whereas the

 

English have sought ISO certification

In Denmark the Association of Con-

 

sulting Engineers (FRI) has rejected

210

the ISO standard, arguing that it does

with it. Additional companies had be-

not cover all the critical elements of a

gun to implement the standard. This

knowledge-based service. As a conse-

tendency is substantiated by a survey

quence of this position, dialogue be-

of the European Construction Institute

tween ISO and FRI has ceased.

(ECI), 52 % of whose members -

Only one consultancy had been certi-

contractors, consultants and clients -

fied in accordance with ISO 9001. The

replied that they were certified, while

majority of companies have instead es-

11 % were in the process of imple-

tablished a quality assurance system

menting the standard, and 16% ex-

based on the paragraphs in the standard

pressed the wish to do so.

that seemed relevant, supplementing

 

them as required. Several companies

 

have likewise produced cross refer-

 

ences to the ISO standard, as some cli-

 

ents have demanded a quality assur-

 

ance system in accordance with the

 

ISO standard. The standard is, there-

 

fore, used - but always as a reference.

 

Doubt in Germany

 

In Germany, the ISO standard has only

 

recently been introduced and until now

 

only a few contractors have im-

 

plemented it. As yet, no engineering

Fig. 42

consultancy has done so. Several con-

 

sultants stated that they could not un-

In conversations with English consul-

derstand the necessity of the ISO stan-

tants it was not unusual to hear that

dard. The general opinion of those

they had/in fact, no expectations for

questioned was that the way the Ger-

substantial positive effects from imple-

man construction industry and the DIN

menting the standard. It is seen as a

standards are related makes the ISO

necessary evil, one which enables con-

standard superfluous.

sulting engineers to qualify for projects

Activity in England

where the client demands the ISO

certificate. The standard and the quali-

 

ty assurance system it promotes are

The attitude towards the ISO standard

thus seen as a dubious formality, use-

(BS 7550) in England differs dramati-

ful only as a marketing tool.

cally from the other two countries

The real value of ISO certification

studied. Nearly 40 % of the companies

seems limited. Both clients and consul-

in the survey had implemented ISO

tants who were surveyed agreed that

9001 and were certified in accordance

ISO 9001 certification does not actual-

211

ly ensure better quality, but only that

sultancies. The standard was drawn up

certain

documented guidelines

had

for manufacturing companies with tan-

been followed.

 

 

gible end-products. As the standard

In England, a small industry has grown

only covers the critical processes for

up around the standard. Around 6000

that type of production, it is not certain

persons now work on implementing,

that it is suitable for knowledge-based

certifying and maintaining quality as-

services like an engineering con-

surance systems.

 

 

sultancy. The critical processes are not

No Extra Fee

 

 

necessarily the same, so the question

 

 

is: How relevant is the standard for

 

 

 

 

 

consultancy. This can be illustrated in

Is a client willing to pay extra for this

Fig. 42.

 

 

extra initiative? A survey carried out

The differences between product-based

by Prof. Peter Barrett, Salford Univer-

and knowledge-based endeavors are

sity, England, shows that only 3% of

considerable. The main reason for this

clients take quality assurance into ac-

is the cognitive and iterative aspects of

count when they select consultants. 95

consultancy. The process is difficult to

% of the cornpanies and clients sur-

forecast

and

schematicise, which

veyed did not expect a higher price for

makes it problematic to assure quality.

the services of a certified company.

The process of the work of an engi-

Many employees still repudiate the

neering consultancy is illustrated in

quality assurance system, and many

Fig. 43.

 

 

companies are still not working consci-

 

 

 

entiously with the system. There is, for

 

 

 

example, no

widespread information

 

 

 

about the costs of ISO-certified quali-

 

 

 

fy. In all three countries, only the ex-

 

 

 

penses of internal and external audits

 

 

 

are registered. Only in Denmark are

 

 

 

expenses such as compensation and

 

 

 

reparations

registered. In

all

three

 

 

Fig. 43

countries, however, there is no existing

 

 

standard

as an alternative

to the ISO

Revision of ISO 9000

9000 standard.

 

 

 

 

 

 

 

Is ISO

9001 Applicable

for

Engi-

The complications stemming from the

neering Consultancies?

 

 

iterative

work

process has been con-

 

 

sidered by the ISO/TC 176 Task Force

 

 

 

 

 

Given the scepticism of so many of the

when it started to revise the ISO 9000

respondents in the study, it is reason-

standard. The standard has been split

able to question if the ISO standard is

up into four main areas:

indeed applicable for engineering con-

- Hardware

 

212

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]