Grouting operation

External prestressing tendon

Wax injected further « circulaire n° 2001 » - a1 type

82

Good practice in PT works

1.Duct Installation

1.1Important aspects:

Following the design profile and securing the position of the duct

Maintaining the original shape of the duct during installation and concreting

Proper duct connections

Good design coordination the post tensioning and reinforcement

87

Good practice in PT works

1.Duct Installation

1.2Possible problems

Friction points

Deformation of duct cross section

Damage of the duct

Improper duct connection

Duct displacement

Clashing of rebar and duct

Clashing of ducts

88

Good practice in PT works

1.Duct Installation

1.3Preventive measures

Sufficient duct supports

Duct connections

Connection to the trumplate

Thorough check of the duct before casting of concrete

Monitoring the tendons during and immediately after casting

Order of design

89

Good practice in PT works

3.Stressing

3.1Important before commencement:

Inspection of concrete surrounding the stressing zones

Friction test

Inspection of blocks, wedges

97

Good practice in PT works

3.Stressing

3.2Possible problems:

High elongation before achieving the required force:

Slippage of wedges

Broken wires or strands Insufficient elongation of tendon

98

Good practice in PT works

3.Stressing

3.3Preventive measures:

Experienced operators and good equipment

Steady application of force and monitoring of results

Good coordination between stressing teams

Monitoring of tendon during stressing

Monitoring of tendon after stressing

99

Good practice in PT works

4.Grouting

4.1Preparation for grouting:

Cutting of strand over-length

Testing of tendon:

All vents are clear

Tendon is clear and propulsive

Sealing of anchorage zone:

Secondary concrete

Temporary grout caps

Permanent grout caps

10