![](/user_photo/_userpic.png)
2383
.pdfThese strands were placed and tensioned one-
by-one. Individual placement was extremely economical, but tensioning required a new
technique, already developed by the cable
supplier for the erection of three bridges: the
Arrade and Guadiana Bridges in Portugal,
and the Chalon-sur-Saone Bridge in France.
The fast strand of each cable is tensioned to a
computed value and equipped with a pressure cell which gives the tension at any time. Each
new strand, when installed, is tensioned to
have exactly the same tension as the pilot strand at that precise moment, which is given by the cell. All strands thus receive the same
tension, which is the desired one if the initial
tension of the pilot strand had been appropriately computed. If not. an adjustment
is made the same way. This process is not
susceptible to influences from temporary operations, such as the movement of construction equipment.
Finally, cables received an external duct made of a series of two half-ele- ments which are forced into each other. These ducts are not for corrosion protection; they are air and water permeable. They aim at reducing drag
forces and avoiding rain-induced vibrations of the cables. In addition, they totally eliminate the vibrations of strands in the bunch which makes each cable, which are produced by wind interaction between strands by a kind of "wake" effect.
Interconnecting Ropes
In his design for the Messina Straits, Fritz Leonhardt envisioned connecting all cables in each plane of the cables by tying ropes, which aimed at increasing the apparent modulus of elasticity of the suspension, lowered by sag effects in long cable-stayed spans. In some other bridges, such as the Faro Bridge in Denmark or the two cablestayed bridges of the Kojima-Sakaide route of the Honshu-Shikoku link, ropes were, installed to limit cable vibration which was rain-induced in the Faro Bridge and coming from the wake effect in the Japanese bridges.
The purpose is totally different in the Normandie Bridge: due to the very, long span of the bridge, the main vibration period for vertical bending would have been of the same magnitude as the vibration period of the longer cables, 4.5 s, compared to about 4.0 s. In this situation, it was feared that cable vibrations would be induces by the deck movements. Interconnecting ropes were designed to totally change the vibration periods of cables, at least transversally, reducing them to 1.25 s and less.
Four ropes connect all cables in each plane of stays. Their tension was selected to avoid de-tensioning from vi-
brations produced by wind turbulence. |
sketches and of premature options and |
||
Their constitution is composite, with |
decisions. |
||
steel and plastic to increase fatigue re- |
Although there was no public money |
||
sistance because it is obviously diffi- |
in the Normandie Bridge, the French |
||
cult to simultaneously achieve a high |
government had to approve the project. |
||
damping coefficient and a high fatigue |
The Road Director at the time, lean |
||
resistance. |
|
Berthier, decided to invite an as- |
|
Concluding Remarks |
essment of the design by an |
||
international group of experts: Marcel |
|||
|
|
|
Huet (Project Manager of the |
The design and construction of very |
Tancarville Bridge), Henri Mathieu, |
||
large bridges which go beyond existing |
Charles Bngnon, Roger Lacroix, Rene |
||
limits require the strongest determina- |
W'alther and Jorg Schlaich. This group |
||
tion from the Owner, who must invest |
proposed various amendments, some |
||
enormous confidence in, and support |
of which were included in the final de- |
||
of, the engineers in charge. The most |
sign. |
||
dangerous |
tempests |
that audacious |
Nevertheless, some engineers from one |
projects face are not produced by wind |
of the erection contractors considered |
||
on site, but by antagonistic opinions |
the wind forces to have been un- |
||
that find a willing audience. |
derestimated and, thus, the safety |
||
The success of the Normandie Bridge |
questionable. The debate became pub- |
||
is due in large part to the confidence |
lic, even international. |
||
and support that the project received |
The Owner and the Road |
||
from the Owner, the Road Director and |
Director decided to consult Alan |
||
the local authorities. Some organi- |
Davenport to evaluate the wind tunnel |
||
sational aspects and some episodes |
tests and the estimated wind forces. He |
||
during construction indicate the deci- |
approved the performed analyses and |
||
sive importance of human factors. |
recommended some additional wind |
||
The Owner gave the design engineers |
tunnel, tests, the results of which were |
||
total responsibility for the design and |
even more favourable than the first |
||
granted them complete freedom to as- |
evaluations. This confirmation of the |
||
semble the design team. Under these |
design helped the project very much, |
||
circumstances, improvements could be |
and from the summer of 1991, all |
||
introduced at each step of the project, |
contractors worked with enthusiasm |
||
with no consideration other than effi- |
and energy to complete the bridge on |
||
ciency. This is far superior to design |
schedule, within budget and up to the |
||
competitions, now preferred by some |
prescribed standards of quality. |
||
administrations, where projects can be |
Any decision can be questioned, any |
||
selected based not always on structural |
action criticised. The clear conclusion |
||
; aspects, and where designers can |
is that a complex and ambitious project |
||
become |
prisoners |
of their initial |
like the Normandie Bridge cannot be |
|
|
|
successfully realised without a strong |
Project Manager - as Bertrand |
Structures |
and Buildings, |
August, |
|||||||||
Deroubaix has been for this project -to |
1993, pp. 281-302. |
B. Presentation |
||||||||||
guide it over the years from conception |
[6] DEROUBAIX, |
|||||||||||
to completion, even when questioned |
du projet et developpement de la |
|||||||||||
from many sides. Going further than |
constructio . In: Le point sur le Projet |
|||||||||||
ever before in any given field calls for |
du Pont de Nor mandie. Annales de |
|||||||||||
courage. The Owner and the local |
1'ITBTP, Paris, September-October |
|||||||||||
authorities remained |
totally |
confident |
1993. |
|
|
|
||||||
in the design and in the engineers in |
[7] LEGER, P. Finaiicvment du Pont |
|||||||||||
charge, even in difficult times. This |
de Normandie. ibid. |
|
|
|||||||||
was decisive for success; complex |
[8] DAVENPORT, A. Analyse des |
|||||||||||
structures cannot be built with |
etudes des effets du vent sur le Pont de |
|||||||||||
hesitations and doubts! |
|
|
|
Normandie. ibid. |
|
|
||||||
References |
|
|
|
|
|
|
[9] VIRLOGEUX, M. Le projet du |
|||||
|
|
|
|
|
|
|
|
|
||||
[1] |
VIRLOGEUX. M.; |
FOUCRIAT, |
Pont de Normandie. ibid. |
|
||||||||
J.-C; DEROUBAIX, B. Design -of the |
Owner: |
|
|
|
||||||||
Normandie Cable-Stayed Bridge near |
Chambre de Commerce et d'lndustrie |
|||||||||||
Honfleur. Proc. of the Int. Conf. on |
du Havre |
|
|
|
||||||||
Cable-Stayed Bridges, Bangkok, pp. |
Project Management: |
|
||||||||||
1111-1122, November, 1987. |
|
|
|
|||||||||
[2] V1RLOGEUX, M. Projet du Pont |
Mission du Pont de Normandie |
|
||||||||||
de Normandie, Conception generate de |
|
|
|
|
||||||||
I'ou-vrage. Proc. of the 13th IABSE |
Design: |
|
|
|
||||||||
Congress, |
Helsinki, |
IABSE, |
June, |
SETRA, |
Sofresid, |
Quadric, |
SEEE, |
|||||
1988. |
|
|
|
|
|
|
|
Sogelerg, Setec and Europe-Etudes |
||||
[3] DEROUBAIX, B.; VIRLOGEUX, |
Gecti. Architect: Charles Lavigne |
|||||||||||
M. |
|
|
|
|
|
|
|
|
|
|
|
|
Design and Construction of the |
Wind Laboratories: |
|
|
|||||||||
Normandie Bridge. Proc. of the IABSE |
CSTB and ONERA |
|
|
|||||||||
Symposium, |
St |
Petersburg, |
Russia, |
Contractors (concrete): GIE du Pont |
||||||||
September 1991. |
|
|
|
|
|
|||||||
[4] VIRLOGEUX, M. Wind Design |
du Normandie (Bouygues, Campenon |
|||||||||||
and Analysis for the Normandie |
Bernard, |
Dumez, |
GTM, Quillery, |
|||||||||
Bridge. In: 'Aerodynamics of Large |
Sogea. Spie Batignolles |
|
||||||||||
Bridges,' |
A. |
Larsen, |
ed. |
Balkema, |
Contractors (steel): |
|
|
|||||
Rotterdam 1992, pp. 183-216. |
|
|
|
|||||||||
[5] |
VIRLOGEUX, |
M. Normandie |
Monberg and Thorsen |
|
||||||||
Bridge: |
Design |
and |
Construction. |
Sub-contractors: |
|
|
||||||
Proc. of |
the |
Inst. |
of |
Civil |
Engs, |
|
|
|||||
|
|
|
|
|
|
|
|
|
Bilfinger -\ Berger, Freyssinet, Munch, |
Lozai,VSL, SDFM |
Service date: |
|
January 1995 |
THE RAINBOW BRIDGE, JAPAN
Kazuo Yamazaki, Mgr, Design and Design Div. Mitsunobu Ogihara, Research Div. Kimihiko Izumi, Mgr, Chief, Design Div. Metropolitan Expressway Public Corp., Tokyo,
Japan
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ195x1.jpg)
Introduction |
The bridge is a 3-span, 2-hinge stiffen- |
The Rainbow Bridge has become a |
ing truss suspension type with a centre |
new landmark in the Port of Tokyo. |
span of 570 m and a total length of 798 |
The bridge provides direct access |
m (Fig. 30). It has a double deck |
between central Tokyo and a wa- |
construction: the upper deck carries |
terfront development now under con- |
two two-lane expressways while the |
struction. It also connects two express- |
lower carries two two-lane roads serv- |
ways on both sides of the Port, creating |
ing the Port, as well as a railway and |
the first express route across the city |
footpaths (Fig. 31). The diameter of |
and is expected to significantly ease |
the main cable is 762 mm. |
traffic congestion in the centre of |
|
Tokyo. |
|
Fig. 30
The bridge is founded on mudstone |
for the Port of Tokyo crossing to satis- |
(consolidated silt or soft rock) far be- |
fy three significant constraints: |
low the surface. Few suspension |
- 500 m wide ship access with 50 m |
bridgeshave their foundations on |
clearance |
mudstone and several innovative tech- |
- main tower height, including erec- |
nologies were employed to overcome |
tion equipment, of less than 155 m due |
this unfavourable condition. |
to the proximity (9 km) of Haneda |
Planning |
International Airport. |
- limited length for the side spans to |
|
|
link up with existing expressways on |
A suspension-type bridge was selected |
both sides of the bridge. |
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ196x1.jpg)
A cable-stayed bridge could have been considered for the 570 m span, however the height of the towers for this type of design would have been about 200 m. Besides, a cable-stayed design would have suffered excessive negative reaction (uplift) at the link shoe of the side spans. For these reasons and economic considerations, a suspen- sion-type bridge was determined to be the best choice.
Fig. 31
Substructure
The water depth at the site is approximately 12 m, and the subsurface ground consists of a weak alluvial clay layer on top of a mudstone stratum. The mudstone bearing layer was found at levels between -30 and -38 m.
Pneumatic caisson foundations were designed and constructed for the two
main towers and the two anchorages. The anchorage caissons are 70 m X 45 m. One anchorage caisson v as constructed at sea using a steel box caisson prefabricated in a shipyard; the other was constructed on land.
For the pneumatic caissons, robotic excavation was employed. A computercontrolled caisson shovel was operated remotely using a video camera. Excavated materials were placed onto an automatic belt conveyer for removal. This method ensured worker safety and construction efficiency under the high atmospheric pressure (3.5 bar) in the caisson's chamber. In addition, special digging machines were used for the excavation of the hard mudstone.
Since an anchorage would be subjected to a huge eccentric force due to the cable tension (230 MN) a precise prediction of long-term (100 years') deformation of the mudstone bearing layer was essential) The initial prediction was modified repeatedly using a measured displacement at each construction stage, and the values obtained were considered in the design of the superstructure.
Item |
Content |
|
|
Type of bridge |
3-span, 2 hinged-stiffening truss, doubledeck suspension |
girder |
|
Span layout |
Stiffening truss: 107.5 + 562.0 + 107.5 m |
|
Cable: 147.5 + 570.0 + 147.0 m |
Tower works |
|
Structural type: |
Longitudinal direction: flexible hinge at top of tower |
|
Transverse: 3-story frame rigid (1 story above road) |
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ197x1.jpg)
Tower height: |
121.866 m (cable theoretical top: 126.0 m) |
|
|
Height of tower |
P36 |
(Shibaura Main Tower): 2.866 m |
|
foundation: |
P37 |
(Daiba Main Tower): 4.5 m |
|
Centre distance |
P36 |
(Shibaura Main Tower) at foundation: |
30.862 m |
between towers: |
|
at tower top: |
30.084 m |
|
P37 |
(Daiba Main Tower) at foundation: |
30.851 m |
|
|
at tower top: |
30.084 m |
Cable works |
|
Cable type: |
PWS (parallel wire strand) |
Structure |
Main span sag: /= 57.6 m; sag ratio: n = 1/9.9 |
dimensions: |
Centre distance between cables: 29.0 m |
Cable diameters: |
Main span: 762 mm; 127 strands per cable |
|
Side span: 771 mm; 130 strands per cable |
Strand: |
Diagonal; 69.8 mm 0 |
Wire: |
5.37 mm 0; tensile strength: 160-180 kg/mm2 |
Hanger rope: |
Centre Fit Rope Core (CFRC); 4 ropes/panel point |
|
|
Stiffening girder works |
|
Structural type: |
Main structure: parallel chord Warren truss |
|
Lateral bracing: K-truss |
Hanging type: |
Anchoring to upper chord |
Structure |
Main structure height: 8.9 m |
dimensions: |
Main structure width: width: 29.0 m |
Upper floor |
Expressway (multi-span continuous steel deck |
system: |
girder, effective width: 9.25 m) Note: Main span is |
|
of 56 span continuous structure, rigidly connected at |
|
both ends |
Lower floor |
Port roadway (multi-span continuous steel deck |
system: |
girder, effective width: 7.5 m, including walkway |
|
1.5-2.5 m wide) |
|
Rail transportation system (multi-span continuous |
|
steel deck girder, RC track gauge: 1.7 m) |
Table 3: Basic structural specifications
The concrete volume of each anchor- |
ing in temperatures of about 3°C for |
age, including the top slab of the cais- |
the sand and -27 to 15 °C for the grav- |
son, amounted to 60000 m3. In order to |
el. Finally, preset water pipes further |
reduce cracking caused by the heat of |
helped to cool the mix after placement. |
hydration, an ultra-low-heat cement |
Superstructure |
was used. In addition, liquid nitrogen |
|
was sprayed onto the aggregate, result- |
|
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ198x1.jpg)
The steel weights for the superstructure included 14100 t for the towers; 83001 for the cables, 23 7001 for the stiffening girders. The basic specifications for the tower, cable and stiffening girder works are shown in Table 3.
main cables, free-standing towers of suspension bridges experience vibration due to wind forces. Based on wind tunnel tests, damping devices including an active mass damper, were installed at the tower tops to resist possible vortex-excited vibration.
A main cable consists of 130 strands (each composed of 127 wires) in the side spans and 127 strands in the centre span. Since the short side spans of the Rainbow Bridge might have encountered a problem due to unbalanced tensile forces in the main cables on each side of two towers, three additional cable strands were installed in the side spans to balance the stress level in the main cable. In addition, a "horizontal frictional board" with an increased surface friction coefficient was fitted to the towers' top cable saddles to further resist cable slippage due to any unbalanced tension. After erection of the strands, the cable was shaped using a squeezing machine.
The Rainbow Bridge also features a multi-continuous (56-span continuous) steel deck floor system with improved shoes on its upper deck. There are no expansion joints in the centre span of the expressway, resulting in a comfortable driving surface and reduced maintenance requirements.
AESTHETICS
Fig. 32
The main towers (Fig. 32) are made of hollow steel box section and were each assembled in three large blocks using 33001 and 41001 (hanging weight) floating cranes. Until erection of the
From the outset, the owner was very conscious of the environmental and visual impact of the bridge, given its prominent location in the Port of Tokyo. A Committee on Aesthetics was established and much attention
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ199x1.jpg)
was paid to architectural and structural |
illumination |
design, |
the |
Rainbow |
|||
details throughout the design and |
Bridge was awarded the Paul |
||||||
planning of the crossing. |
|
|
Waterbury Award of Distinction for |
||||
The rounded corners and reduced bolt |
Outdoor Lighting by the Illumination |
||||||
connections of the main towers' |
Engineering Society of North America. |
||||||
columns and beams, as well as the con- |
Owner/Engineers: |
|
|
||||
figuration and surface finish of the an- |
Metropolitan |
||||||
chorages, resulted from aesthetic con- |
Expressway |
Public |
Corp. |
(MEPC), |
|||
siderations. The graceful configuration |
Tokyo |
|
|
|
|||
of the bridge is illuminated at night by |
Construction duration: 6.5 years |
||||||
white, green and coral pink lighting. |
|||||||
The lighting pattern varies with the |
Service Date: August, 1993 |
|
|||||
seasons and times of day. For its |
|
|
|
|
|||
THE TÄHTINIEMI BRIDGE, FINLAND |
|
|
|
||||
|
|
|
|
land, with a total length of 924 m. The |
|||
Esko Jarvenpaa, Technical Dir. |
|
main span is 165 m and the width of |
|||||
Pekka |
Pulkkinen, |
Civil |
Eng. |
the deck varies from 22 to 30 m. |
|||
Suunnittelukortes AEK |
Ltd, |
Oulu, |
|
|
|
|
|
Finland |
|
|
|
|
|
|
|
Reiner Saul, Managing Dir. |
|
|
|
|
|
||
Leonhardt, Andra and |
Partner, |
|
|
|
|
||
Stuttgart, Germany |
|
|
|
Fig. 33 |
|
||
|
|
|
|
|
|
INTRODUCTION |
DESIGN COMPETITION |
In 1988 the Finnish Roads Administra- |
The competition was limited to four |
tion organised a design competition for |
Finnish bridge engineering companies. |
a technically advanced bridge which |
The design brief was very demanding. |
would adapt well to the lake landscape |
Among the most important parameters |
near the city of Heinola. Heinola is one |
were the site, the difficult foundation |
of the most beautiful cities in Finland, |
conditions, the curvature of the |
about 130 km north of Helsinki on the |
roadway and the need to maintain free- |
route to a lake area where many |
flowing marine traffic, including a |
vacation cottages are located. |
busy logging channel. Maximum water |
The winner of the competition, now |
depth at the site is 24 m, and the bridge |
known as the "Star of Heinola", is a |
is situated in a natural lake landscape, |
single-pylon cable-stayed bridge (Figs. |
near the town. |
33, 34). It is the largest bridge in Fin- |
|
![](/html/65386/418/html_wXQisQ4XIc.8B1F/htmlconvd-rEq1UQ200x1.jpg)
Ten proposals were delivered to the |
was required, there were inclined steel |
competition jury. Five were traditional |
struts in the cross sections of two steel |
composite girder designs; one was a |
girder designs for this type. |
single pylon design and three were |
The cross section alternatives for the |
double-pylon cable-stayed designs. |
cable-stayed bridge designs were a |
There was also one truss bridge pro- |
concrete box girder, a composite gird- |
posal. |
er, a composite box girder and a com- |
In the superstructures of the composite |
posite slab beam which was pre- |
girder bridges, reinforced compression |
stressed in two directions. |
slabs were used in the areas of the |
The foundation solutions were very |
intermediate supports, and longitudinal |
similar in all bridges. In deep water, |
prestressing in the deck slab. Due to |
composite steel pipe piles were used. |
the considerable width of the deck that |
|
Fig. 34
Other supports were founded on soil or |
signed for far heavier traffic loads than |
rock. The diameter of the piles varied |
current Finnish load codes specify. |
from 700 to 1500 mm. |
Deviating from Finnish load specifica- |
The winning design, with its single |
tions, the full traffic load can be car- |
105 m high pylon, serves as a dramatic |
ried on one side of the bridge deck |
gateway to the lake district of Finland. |
when there is simultaneously a special |
Its cable-stayed spans are placed over |
heavy truck on the other. If the cables |
the open lake so that the heavy marine |
have to be changed in the future, only |
traffic can operate with minimal ob- |
one edge lane has to be closed. Also, |
struction. |
the pylon was designed for greater |
|
wind loads than specified in the |
BRIDGE DESIGN |
existing code. Crash loads of ships |
|
have been taken into consideration in |
The client wanted to assure adequate |
the design of the intermediate support. |
traffic-handling capacity of the bridge |
The five middle supports are founded |
far into the future as well as under ex- |
on composite steel pipe piles; other |
ceptional circumstances. Thus, it was |
supports are founded on soil or rock. |
decided that the bridge should be de- |
The steel piles were designed as a |