Добавил:
Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2383

.pdf
Скачиваний:
10
Добавлен:
07.01.2021
Размер:
6.86 Mб
Скачать

composite structure with a 4 mm thickness of the steel pipe wall allowed for corrosion. The diameter of a pile is 813 mm and thickness is 16 mm. Reinforcing bars are placed in the uppersection of the piles.

The cross section of the deck is a traditional composite structure of two open girders. The girders are 3.2 m high I- beams (Fig. 33). There are crossbeams at 7 m centres. On the crossbeams there is a 1 m high secondary longitudinal girder. In the north part of the bridge, where the deck is 30 A wide, there are two secondary girders.

The cable crossbeams are inclined to the cable direction. Between the main girders, the cross section of the cable crossbeam is an open I-beam. The girders are stiffened with steel bars. Outside the main girders, the cable crossbeam is a composite box girder.

In the competition proposal, the pylon was a steel structure. In the general design, the costs of steel, composite and concrete pylon were compared. The concrete pylon proved to be the most economical.

The pylon is formed of two T-shaped hollow concrete towers which are joined together by two crossbeams. There is an elevator inside one tower and stairs inside the other. The horizontal geometry of the road has a curvature of R = 4000 m. This caused large horizontal forces on the towers. Therefore, the pylon was not placed centrally to the deck cross section, but with an eccentricity of 0.6 m. Due to this placement, the horizontal forces, and hence, the number of steel piles decreased considerably.

The bridge has 24 factory-fabricated parallel wire cables. The cables consist of 7 mm steel wires (253-403/cable) injected with grease inside a high density polyethylene pipe that is covered with white Tedlar tape. The pylon and cables are illuminated at night.

The fixed bearing of the bridge is at the southern abutment. It is a hinged structure, where horizontal forces are transferred large steel bars.

CONSTRUCTION

The piling and the concreting of the foundation slabs and columns took 14 months. The joint welding of the steel girder sections and the launching were completed in one year. The largest concrete works, such as towers and deck slabs, were placed in summer, because the temperature in winter can be as low as -25 °C.

At the beginning of the construction period, the design for the pile foundation was changed to a caisson structure. The caissons were built in a dammed trough on the north side of the bridge. The caissons were floated into position and the piling work was done through access holes in the caisson slab. Finally, the piles and the inner part of the caisson were cast in dry conditions. Except for the slab of supports T3 and T9, all casting work on the substructure was done in dry conditions. The casting of pile slabs succeeded well and there were no faults typical of underwater concrete casting.

The steel girders of the superstructure were launched from both abutments

and joined by welding between supports T5 and T6. Three auxiliary piers had to be built for the cable:stayed spans during launching. The top of the girder was lifted on a pontoon when the spans exceeded 70 m. The launching bearings were vertically adjustable because the girder was very stiff. The longest beam sections were 42 m long and the maximum weight was almost 80 t.

The bridge was originally designed using steel grade Fe 355 E, but the steel contractor and steel manufacturer proposed to change the steel grade of the support sections of the girder to a new thermomechanically manufactured S 420 ML steel. Using this material, the contractor slightly reduced the weight of the girder and benefited from the superior welding properties of the new steel grade. The total amount of steel in the superstructure is about 50501.

The towers of the pylon were cast using a climbing formwork, with the height of one casting section being 4.15 m. The longitudinal reinforcing bars were jointed with screw sleeves.

The crossbeams between the towers and the cable anchor areas were pre: stressed. The surface of the concrete tower had to meet stringent quality requirements. A textile covering was placed on the formwork surface to enhance the strength of the concrete surface and to reduce air blisters. A green concrete paint was applied to the surface of the pylon.

Construction of the pylon was complicated because it has three inclined walls. Therefore, the scaffolding had to be adjusted at every stage. The

reinforcing of the cable anchor area was difficult because of restricted space. The temporary support structure of the upper crossbeam was also difficult to install and there were problems to stabilise it. Nevertheless, the pylon was completed on schedule and all casting work was completed before winter.

The deck slab of the superstructure was cast using two movable scaffolding units. The longest casting section was 24 m. The slab was prestressed transversely in two equal stages.

The stay cables were installed from the bottom upwards. Cable stressing was accomplished using four jacks at the level of the deck slab. The cables were stressed in pairs. The total weight of stay cables is 214 t. They were tested against fatigue and ultimate load, the test cable being the largest cable of the bridge. In the fatigue test, where a 5 m long test Cable was loaded 2 million times with a stress variation of 193 MPa, only 9 wires broke. After this test the same cable was stressed up to the breaking load, 24.6 MN.

Client:

Mikkeli Road District

Design:

Suunnittelukortes AEK Ltd, with Leonhardt, Andra and Partner

Main contractor: WT Corporation Ltd

Steel contractor: PPTH Steel Ltd

Construction duration: January 1991 to November 1993

The Pitan Bridge, Taiwan

Kwong M. Cheng

 

 

constraints and concerns that guided

Pres.,

OPAC Consulting

Engineers,

the design of the bridge, it had to:

San Francisco, CA, USA

 

- meet all freeway design and perfor-

Introduction

 

 

mance requirements of the Northern

 

 

Taiwan Second Freeway

 

 

 

 

 

-

be

aesthetically

pleasing,

To alleviate traffic congestion near

constructable, and economical

 

Taipei, in 1985 the Taiwan Area Na-

- require minimum maintenance.

tional Freeway Bureau planned the

The following factors were considered

construction of the 108 km long North-

in the selection of the bridge type:

ern Taiwan Second Freeway. The ma-

-

Structural systems issues such as

jority of the Second Freeway's align-

bridge piers, span lengths and

ments are on grade, on embankments,

arrangement, foundations, vertical and

in tunnels, or on viaduct structures. At

horizontal clearances, capacity to resist

several

locations,

however,

obstacles

horizontal forces and seismic actions,

were identified that required special

etc.

 

 

bridges. The Pitan Bridge spans one of

-

Aesthetic issues such as the overall

these areas.

 

 

appearance of the bridge, its com-

The Pitan Bridge, actually two nearly

patibility with the surrounding land-

parallel bridge structures, is located

scape and with existing built facilities

about 15 km south of Taipei. It

- Construction issues such as the con-

connects typical low-level viaducts to

struction method, equipment, con-

a tunnel. Both bridge units have a total

struction time and the capabilities of

length of approximately 800 m, a 750

local contractors

 

m radius curvature and a slope of

- Cost issues such as the cost of relat-

approximately 1%. The Pitan Bridge

ed

works,

of maintenance

and the

has become a landmark in this subur-

cost of the bridge itself.

 

ban area of Taipei.

 

 

Four bridge types consisting of varia-

SELECTION OF THE BRIDGE

tions on girder-and-arch designs were

identified as potentially meeting the

TYPE

 

 

 

above design considerations.

 

 

 

 

 

The selected bridge type consists of a

The design of the Pitan Bridge was

post-tensioned cast-in-place concrete

based primarily on the 1983 AASHTO

box girder bridge deck supported on

Standard Specification for

Highway

delta-shaped reinforced concrete box

Bridges, the 1987 AASHTO Design -

piers, which are joined together at the

and Construction

Specifications for

centre of the main span to form an

Segmental Bridges (No. 2 Draft), and

arch. This scheme adapts well to the

local design codes. Among the general

constraints of the site and provides a

stiff, strong bridge with a clean, effi-

structural layouts. They each consist of

cient, and very modern appearance.

nine spans totalling 781.5 m, with a

BASIC LAYOUT

160 m main span. The northbound

bridge has an additional simple span of

 

21.7 m (Fig. 35).

The two almost parallel bridge structures have nearly identical

Fig. 35

Expansion joints have been kept to a

The preliminary design made use of

minimum, located only at the extreme

simple and rational analytical tools that

ends of the structure. The four main

have proven reliable for many

bridge piers (3, 4, 5 and 6) are fixed to

structures. The following were consid-

the girder and footings with monolith-

ered at this stage of the design in order

ic, moment-resisting connections. The

to determine the dimensions of the

smaller piers and the abutment are

main structural elements of the bridge:

fixed to their footings only and support

the cross section, the longitudinal sys-

the girder through bearings that are

tem, the pier shafts, footings and piles.

fixed

transversely,

having

some

SUPERSTRUCTURE DESIGN

limited freedom-to slide longitudinally.

This combination of few expansion

 

joints and high pier fixity was evaluat-

Detailed design and analysis made use

ed for serviceability under the required

of more refined analytical tools in or-

seismic excitation, as well under the

der to verify the preliminary design.

influence of creep and shrinkage in the

The following tasks were performed:

concrete, and temperature change in

- development of structural models for

the

structure.

The

piers

and

service-load analysis

foundations provide enough flexibility

- evaluation of design values for mo-

so that the time-dependent strains and

ment and shear

temperature strains of the concrete,

- transverse and three-dimensional

accumulated over the entire girder

considerations

length between expansion joints, cause

- pier moments, shears, and axial

acceptably small bending stresses in

forces

the piers and axial stresses in the gird-

- thermal effects.

er.

 

 

 

 

The bridge superstructure consists of a

 

 

 

 

 

single cell box girder (Fig. 36). The di-

mensions of the box girder were de-

The web longitudinal prestressing is

signed to comply with the strength re-

dimensioned to provide adequate mo-

quirement as well as provide space to

ment capacity and stress control at

house the necessary prestressing ducts.

mid-span and over the pier to resist su-

The main span girder depth varies

perimposed dead load, live load, creep,

from 8.882 m at the face of the delta-

and temperature moments. Each of

shaped pier to 3.5 m at mid-span, and

these tendons extends over the full

is prestressed longitudinally with can-

length of a span, and is anchored in the

tilever tendons in the top slab and con-

diaphragm walls over the pier.

 

tinuity tendons in the webs. All pre-

The deck transverse prestressing is di-

stressing is grouted in ducts embedded

mensioned to resist transverse bending

in the slabs and webs of the girder.

from dead load and live load. The gird-

 

er cross-section reinforcement includes

 

a grid of mild steel bars in each direc-

 

tion on each face of each structural el-

 

ement.

 

 

 

The delta-shaped piers are designed to

 

reduce the length of the main span,

 

thus allowing the relatively slender

 

box girder to meet the strength and

 

stiffness demands on this bridge. They

 

are designed as wall-type elements

 

with post-tensioning to provide a

Fig. 36

residual compressive stress

under

The top deck longitudinal prestressing

combined axial force and bending for

is dimensioned to resist all structural

all service load conditions. The

dead loads during cantilevering, as

schematic prestressing layout of the

well as construction loads and the

main span is shown in Fig. 37.

 

weight of the travelling formwork. All

SEISMIC

ANALYSIS

AND

anchorages are located in the well-

confined and reinforced intersection

DESIGN

 

 

fillets at the tops of the webs.

 

 

 

Fig. 37

Initial, seismic analyses were perseismic design criteria. These analyses formed in accordance with the local provided controlling conditions for de-

sign of the piers and foundations.

and no plastic hinges develop below

A more refined analysis using earth-

the ground surface.

quake response spectrum developed

Foundations consist of 2.0 m diameter

for the vicinity of the site, was used

drilled, cast-in-place, reinforced con-

later to verify structural dimensions

crete piles, supporting reinforced con-

and reinforcement requirements.

crete footing blocks. The piles, up to

Substructure Design

14 m in length, act as friction piles

with some limited end-bearing support.

Each pier consists of a four-walled cel-

Analysis and Modelling

lular reinforced concrete shaft, heavily

reinforced to form a ductile cellular el-

 

 

ement. All fixed piers participate in

Constructability will largely determine

providing the required capacity to re-

the success of a project. Therefore, a

sist seismic and horizontal forces. For

thirty-eight step stage-by-stage analy-

transverse seismic loads, the piers be-

sis of the bridge was performed to vali-

have as cantilevers, with significant

date the time-dependent behaviour of

moments developed at the bottom

the construction sequence. The analy-

only. For resisting longitudinal seismic

sis included:

excitation, the main piers behave as

-

development of structural computer

members in a rigid frame. The creep,

models for construction procedure

shrinkage, and temperature deforma-

-

evaluation of stresses and deflections

tions of the superstructure are ade-

at critical construction stages

quately accommodated in the mono-

- evaluation of stresses and deflections

lithic piers by the flexibility of the

over the service life of the bridge.

foundations and the pier shafts.

The bridge was modelled using a com-

The basic cross section of the main

mercially available general-purpose

piers continues through the depth of

structural analysis program which is

the box girder cross section to provide

capable of static and dynamic analysis

diaphragms capable of developing the

of finite element models for a wide

plastic moment of the pier into the

range of structure types.

girder. These diaphragms also provide

All important structural features of the

a convenient location for anchorage of

bridge were modelled, including the

the longitudinal prestressing tendons in

piers, the box girder, and the delta-

the superstructure.

shaped piers. The girder was modelled

The abutment is designed as a conven-

as a line of frame elements represent-

tional cantilever wall which supports

ing the entire cross section, oriented

the bridge girder on sliding bearings.

along the centroidal axis of the proto-

The footing blocks supporting the piers

type girder. The piers were modelled

were designed for the static dead and

similarly, including semi-rigid ele-

live impact loads and the seismic loads

ments in the pier-girder intersection.

such that the movements at the base of

The intersection zone between the

the piers are within allowable limits

delta-shaped piers and the girder was

modelled by a separate finite element

distribution between the diaphragms

model in order to capture the stress

and the webs in this area.

ROOSEVELT LAKE BRIDGE, GILA COUNTY, ARIZONA

Maurice D. Miller, Civil Eng.

portant, the deciding factor for the new

HTNB Corp., Kansas City, MO

Roosevelt Lake Bridge was flood

Crossing Roosevelt Lake

protection. When the US Bureau of

Reclamation raised the dam by 23.5 m

 

to provide additional protection to

Located in Gila County, a rugged area

Phoenix and the Valley of the Sun, it

of east-central Arizona, Roosevelt

removed State Highway 188 from the

Lake is a hydroelectric reservoir used

dam.

for flood control, irrigation and recre-

Bridge Type Selection

ation. It is midway between the cities

of Globe, which is the county seat, and

 

Payson, in a ranching and recreational

Located about 305 m upstream of the

area. State Highways 88 and 188 con-

dam, the new Roosevelt Lake Bridge is

nect the two major cities. From Globe,

just below the confluence of the Salt

Route 88 winds northwest through

River and Tonto Creek. Here, the Salt

desert canyons and along the south-

River just begins the erosion of its

west shore of Roosevelt Lake to a ma-

canyon through the Mazatzal Moun-

sonry dam, where it connects with

tains. The steep-walled features of the

Route 188 and continues west and

canyon were ideal for the construction

north to Payson.

of the world's highest masonry dam,

The one-lane road traversing the dam

creating a lake 300 m wide and 60 m

across Roosevelt Lake had not been

deep at the proposed crossing.

improved since construction of the -

The Arizona Department of Trans-

dam in 1911. Travel across the dam

portation based its selection of the best

was slow and treacherous, with abrupt

type of bridge for the crossing on eco-

90° blind corners. When two cars met

nomics. Because of the steep valley

on the dam, one had to yield the right-

walls and the deep valley floor, under-

of-way and back up, a gesture that was

water foundations were determined to

not always made willingly by the local

be too costly. The two-lane bridge

ranchers.

would have to span the lake with foot-

Because of the narrow and crooked

ings on each shore. Two engineering

route over the dam, vehicles over 9 m

firms prepared complete construction

in length were prohibited. Commercial

plans for two alternatives: a steel box-

traffic between Globe and Payson was

rib-through-arch and a concrete stayed

forced to detour through Phoenix,

girder bridge.

adding hundreds of miles to the route.

The box-rib-through-arch was selected

Although traffic congestion was im-

for the steel alternative based on an in-

depth study of three steel bridge types:

box section varies from 2.44 m at the

trussed-through-arch, box-rib-through-

crown, where compressive forces are

arch, and cable-stayed girder. The

the smallest, to 4.27 m at the base,

twisting alignment required for the

where compressive forces are the

mountainous terrain made it difficult to

greatest. The shape of the arch rib was

get a tangent alignment long enough to

also established to minimize the dead

accommodate minimum-length back

load bending stress in the arch. The re-

spans for the cable-stayed and trussed

sultant shape is defined by both second

arch bridges.

order and fourth order curves, making

The arch span was the most economi-

the entire arch appear smooth and

cal. It adapted readily to the curved

continuous.

alignment of the approach structures

The steel arch rib section is made up of

and had superior aerodynamic proper-

two 1.2 m-wide flanges with two web

ties. The welded steel arch was the

plates that vary from 2.44 m at the

overwhelming favorite of most

crown to 4.27 m at the base plate. The

bidders. It was bid at 30% less than the

webs of the box section are stiffened

concrete alternative.

by two T-sections welded to each web.

Arch Rib Design

The stiffeners are continuous and par-

ticipate fully in carrying the various

 

loads. Sixteen longitudinal fillet welds,

Existing terrain and future lake levels

over 13.4 m long, were required to

were important factors in establishing

connect the flanges and the stiffeners

the arch rib geometry. The arch spring-

to the webs.

line is at Elevation 649.5 m, well

Stability against global buckling and

below the 200-year flood elevation of

transmission of wind loads for the arch

663 m. To keep the steel arch above

rib, which is 15.2 m center-to-center,

water, the lower 158 m of the arch rib

was achieved through the use of a K-

is made of concrete. The resulting

bracing system fabricated from struc-

composite steel-concrete structure

tural tubing and welded box sections.

consists of the following sections: 21.6

The selection of the K-bracing was

m of concrete rib, 323 m of steel rib,

based on both first-cost and life cycle

and 21.6 m of concrete rib, for a total

costs. The K-bracing required 901 less

arch rib length of 366.4 m and an arch

steel and reduced wind deflections to

span of 329 m.

half as much as those caused by a

The steel and concrete portions were

comparable Vierendeel system. The

made continuous by anchoring a base

closed tubular sections were selected

plate at each of the steel-concrete con-

to minimized corrosion due to

nections. This required 32 MN of pre-

entrapment of water and debris. To to-

stress force at each base plate.

tally close the ends of the tubular

The geometry of the entire arch rib op-

shapes, horseshoe-shaped plates were

timizes the use of material through the

welded to the ends of the tubes.

length of the rib. The depth of the steel

 

At the portals, the K-bracing was terminated with a three-dimensional X- shaped connection. The multi-jointed, three-dimensional intersection of the bracing was achieved by welding plates into an octagon and welding the ends of the tubes to the sides of the octagon. More than 760 m of fillet welds were used to make up the bracing.

Another part of the bracing system is a 2.1 m square welded box strut between arch ribs directly below the roadway at each end of the bridge. Access to the interior of the ribs is through lockable doors in these boxes. Electrical distribution centers are also inside the struts. The floor system for the 11.5 m wide roadway consists of longitudinal stringers, supported on welded I-girder floor beams. Floor beams are spaced at 15.2 m centers and are hung from the arch ribs with eight wire ropes, four at each end of a floor beam. Welded steel girders 2.0 m deep are used as exterior stringers and also function as stiffening girders for aerodynamic ''stability. About 2.1 m of fillet welds were required to fabricate the floor system. The overall stiffness of the system - arch ribs, bracing, and floor - was verified by wind tunnel tests.

Erection of the bridge was accomplished

using temporary towers resting on the arch footings and a system of bridge strand

backstays and forestays. Hydraulic jacks in

the stays allowed alignment adjustments to be

made during erection.

The erection progressed by lifting and bolting successive 15.2 m long welded steel rib sections into place with a barge-mounted crane floating on the lake. As adjacent rib sections were placed, the welded tubular K-bracing was installed to maintain alignment and rigidity of the ribs. Shop fabrication accuracy was maintained so well that there were no mismatches during erection.

Owner:

Arizona Dept of Transportation

Engineers:

HNTB Corp., Kansas City, MO

Main contractor:

Edward Kraemer & Sons, Inc., Plain, WI

Service date: 1990

ERECTION

BRIDGE SCOUR FAILURES

Introduction

D.V. Mallick M.M.Tawil

 

Technical Advisors

Failure of a bridge is viewed seriously

National Consulting Bureau, Tripoli,

by the public since it involves not only

Libya

traffic disruption and the loss of tax

 

payer's money but can also result in

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]