- •5.3 Test Instructions
- •Table of Allowable Rapid Fluctuations of Certain Key Measurements.
- •5.5.6 Data Verification
- •5.6 Results
- •5.7 Analysis
- •5.7.1 Method of Trending Results
- •5.8 Report
- •HP / IP Turbine Efficiency Test
- •Typical Control Room Data Sheet
- •Point ID
- •Condenser
- •Annexure - I
- •CONDENSER DESIGN DATA
- •Annexure - II
- •TEST READINGS
- •Annexure - III
- •TYPICAL CONTROL ROOM READINGS
- •UNITS
- •kcal/hr
- •3.0 Working And Test Set Up
- •TEST ENGINEER (TE):-----------------------------------------
- •ENGINEERING REVIEW
- •PERSONNEL REQUIRED
- •TEST CREW ORIENTATION
- •REFERENCE DRAWINGS
- •LEAK DETECTOR OPERATION
- •TEST LOG
- •ACCESSIBILITY
- •CONTROL ROOM / UNIT DATA
- •LIST OF INSTRUMENTS & ACCESSORIES REQUIRED FOR AIR-IN-LEAK TEST
- •L. P. Turbine
- •*Total time from leak sensing by instrument to retrieval to zero (0)
- •Unit
- •LOW FEED WATER TEMPERATURE
- •EXCESSIVE MAKEUP
- •HIGH WATER LEVEL
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •HIGH DRAIN COOLER APPROACH TEMPERATURE (DCA)
- •DRAIN COOLER INLET NOT SUBMERGED
- •IMPROPER SETTING
- •EXCESSIVE TUBE BUNDLE PRESSURE DROP
- •HP Heater Test Data
- •Control Room Readings
- •FAULT TREE
- •LP Heater Test Data
- •Control Room Readings
- •FAULT TREE
- •LOW FEED WATER TEMPERATURE
- •EXCESSIVE MAKEUP
- •WORN VENT
- •HIGH WATER LEVEL
- •TUBE LEAKES
- •HEADER PARTITION LEAKS
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •HIGH DRAIN COOLER APPROACH TEMPERATURE (DCA)
- •DRAIN COOLER INLET NOT SUBMERGED
- •IMPROPER SETTING
- •EXCESSIVE TUBE BUNDLE PRESSURE DROP
- •EXCESSIVE NUMBER OF TUBES PLUGGED
- •Unit
- •BFP Test Data
- •Typical Control Room Readings
- •Boiler Feed Pump A / B / C
- •Typical DAS Readings
- •Description
- •CONTENTS
- •1.0 Introduction
- •3.1 Process Description
- •4 References
- •4.1 ASME Performance Test Code 4.2 – 1969, Coal Pulverizers
- •5 Prerequisites
- •(A clean air test is performed with the primary air to the mill at full load normal conditions with the mill out of service (normal primary airflow, no fuel flow)).
- •Avg. Velocity
- •6.4 Isokinetic Coal Sampling
- •4.5.2 Unburned in Flyash at Economizer Outlet
- •Summary
- •Dry Gas Loss
- •Gas Temp Leaving AH - Corr. to Design Ambient
- •OBJECTIVE : Determine the amount of Power being consumed by the primary plant equipment.
- •TEST ENGINEER (TE):
- •REFERENCE: ASME PTC 19.6-1955 and TVA Proc. No. TS/PERF/RTST/FOS/16.0
- •BILL OF MATERIALS
- •BILL OF MATERIALS
- •Note: Quantities to be decided as per the requirement
- •2.4 PORTABLE DATA ACQUISITION SYSTEM
- •BILL OF MATERIAL
- •Acquisition
- •EQUIPMENT: Thermocouple wire for flue gas temperature measurement
- •2.9 HIGH VELOCITY THERMOCOUPLE (HVT) PROBE
- •2.11 HIGH VOLUME FLYASH SAMPLER
Heat Rate Improvement Guidelines
for
Indian Power Plants
Volume II
By:
Center for Power Efficiency and Environmental Protection, National Thermal Power Corporation Ltd.
In Association With
United States Tennessee Valley Authority
For:
United States Agency for International Development and
National Energy Technology Laboratory,
United States Department of Energy
Project Funded by:
USAID/India Greenhouse Gas Pollution Prevention Project (GEP)
Heat Rate Improvement Guidelines
for
Indian Power Plants
Volume II
Revision 1 June 2000
Principal Authors:
S.C. Deo Sharma, D.K. Agarwal, B.M. Singh, P. Bhartiya, L.M. Rastogi, A.K. Arora, M.K.S. Kutty, O.P. Agnihotri and R.J. Tramel
TVA’s Participation Under:
DOE Interagency Agreement No. DE-AI26-97FT97300
“TVA” is a registered trademark of the Tennessee Valley Authority
TABLE OF CONTENTS
1.0Typical Test Procedures
1.1Routine Turbine Efficiency Test
1.2Condenser Performance Test
1.3Condenser Air - In - Leakage Detection Test
1.4HP Heater Performance Test
1.5LP Heater Performance Test
1.6Routine Boiler Feed Pump Performance Test
1.7Routine Pulverizer Performance Test
1.8Routine Air Heater Performance Test
1.9Routine Boiler Efficiency Test
1.10Routine Station Auxiliary Power Survey
2.0Technical Specifications for Performance Test Equipment
2.1Pressure Transmitter
2.2Differential Pressure Transmitter
2.3Resistance Temperature Detector
2.4Portable Data Acquisition System
2.5Gas Analyzer (Carbon Dioxide: Non-Fuel Cell Based)
2.6Gas Analyzer (Oxygen and Carbon Monoxide: Non-Fuel Cell Based)
2.7Integrated Data Acquisition and Analysis System Software (IDAAS)
2.8Thermocouple Wire
2.9High Velocity Thermocouple (HVT) Probe
2.10Air/Fuel Ratio Sampler Kit with Dirty Air Probe
2.11High Volume Flyash Sampler
2.12High Accuracy Glass Thermometers
iii
iv
(For Internal circulation only)
1.1 ROUTINE
TURBINE EFFICIENCY TEST
Procedure No.: CENPEEP/EFF/TP/301
Rev No. |
: 01/EMS |
Issue Date |
: April 20, 2000 |
CENPEEP |
Centre for Power Efficiency & Environmental Protection |
|
National Thermal Power Corporation Ltd. |
A-8A, Sector-24, NOIDA, (U.P.) 201301 India Tel: 011-8-4525197, Fax:011-8-4538874 email: cenpeep@ntpcrd.ernet.in
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 1 |
OF 16 |
CONTENTS
1.0Process Description
2.0Objective
3.0Evaluation Criteria
4.0References
5.0Test Procedure
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 2 |
OF 16 |
1.0Process Description
This procedure provides a systematic method for conducting routine efficiency tests on steam turbine sections operating in the superheated steam region. The test results produce a statistic, which is an expression of the steam turbine section enthalpy drop efficiency.
2.0Objective
The objective of the efficiency test is to provide information to allow accounting for the contribution of steam turbine performance deficiencies on unit heat rate and capacity and to provide a check of accuracy of critical station instruments.
3.0Evaluation Criteria
ASME Performance Test Code 6S –1988 (reaffirmed 1995), Simplified Procedures for Routine Performance Tests of Steam Turbines.
4.0References
ASME Performance Test Code 6 – 1996, Steam Turbines.
ASME Performance Test Code 19.1 –1985, Measurement Uncertainty. ASME performance Test Code 19.2 – 1987, Pressure Measurement. ASME performance Test Code 19.3 – 1974, Temperature Measurement.
5.0Test Procedure
The test method outlined in this procedure is the enthalpy drop efficiency method. The procedure is performed prior to turbine overhaul to provide information to allow diagnosing the steam turbine condition; following overhaul to provide information to allow evaluation of the effects of the overhaul work on steam turbine performance; during normal operation to identify abnormal changes in performance of steam turbines and to provide information to allow identifying the cause of change.
This method determines the ratio of actual enthalpy drop across turbine section to the isentropic enthalpy drop. This efficiency method provides a good measure for monitoring purposes, provided certain qualifications are met in obtaining results.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 3 |
OF 16 |
Each section of the turbine must be considered a separate turbine. For example, a double flow high-pressure section consists of two turbines, the governor end section and the generator end section. Each section must be tested and the results of each trended separately. As well, it is necessary to operate the turbine with the same control valve setting from test to test for the test results to be comparable (preferably at valves wide open); it is also necessary that the feedwater heaters served by the turbine be in service and operated normally, otherwise stage pressure changes will be affected and mask any actual steam path problems.
To ensure accuracy, each independent variable must be controlled, such that all subsequent tests may be related to all previous tests.
5.1Test Instrumentation
The test instrumentation required to conduct the turbine efficiency test consists of temperature, pressure, flow and electric power measurement devices. The number and the type of instruments required depend on the size and configuration of the unit to be tested.
5.1.1Test Instrumentation & Measurements Required (Typical list for 200/210 MW Unit )
Measurement |
Temperature |
Pressure Diff. Pres. |
Electric Power |
|
Feed water |
|
1 |
1 |
|
Main Steam ( L&R ) |
2 |
2 |
|
|
First Stage |
|
1 |
|
|
Extraction HP Turbine |
1* |
1* |
|
|
(as applicable ) |
|
|
|
|
HPT Exhaust ( L&R) |
2 |
2 |
|
|
Hot Reheat Steam ( L&R ) |
2 |
2 |
|
|
Extraction IP Turbine -I |
1* |
1* |
|
|
Extraction IP Turbine –II |
1* |
1* |
|
|
IP Turbine Exhaust ( L&R ) |
1 |
1 |
|
|
Condenser Back Pressure |
|
2 |
|
|
Gross Generator Output |
|
|
|
|
Barometric Pressure |
|
1 |
|
|
Total |
10 |
15 |
1 |
1 |
Note : 1.Extraction number as per station terminology.
2. *-- Instruments to be installed on tappings near turbine.
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 4 |
OF 16 |
5.1.2Instrument Accuracy Requirements
The instruments must be accurate to specifications as listed.
Instrument |
Unit |
Range |
Accuracy |
Remarks |
RTDs |
o C |
0-600 |
Class A |
12 point calibration |
|
|
|
(At 600=1.35 C) |
curve to be used |
Pressure |
kg/cm2 |
0-0.35 |
+ / - 0.075% |
12 point calibration |
Transmitters |
|
|
curve to be used |
|
Pressure |
kg/cm2 |
0-60 |
+ / - 0.075% |
12 point calibration |
Transmitters |
|
|
|
curve to be used |
Pressure |
kg/cm2 |
0-200 |
+ / - 0.075% |
12 point calibration |
Transmitters |
|
|
|
curve to be used |
Diff. Pr. |
kg/cm2 |
0 – 1.5 |
+ / - 0.075% |
12 point calibration |
Transmitter |
|
|
|
curve to be used |
5.1.3Instrument Calibration
Instrumentation required by this procedure will be calibrated once in two years. Typically the calibrations will be performed by an approved laboratory. Calibration records for these instruments will be maintained as permanent records and reference to the current calibration be made in the report.
All station instruments required by this procedure should have current calibrations. The calibration must be traceable to the NIST (National Institute for Standards and Technology). The calibrations may be performed by the plant staff, provided the plant has appropriate instrument standards available to them.
Calibration records for these instruments will be maintained as permanent records.
5.1.4Station Instrumentation Required
Measurement |
Temperature |
Pressure |
Flow |
Electric |
Feedwater |
|
|
Yes |
Power |
|
|
|
||
Reheater Spray |
|
|
Yes |
|
Super heater Spray |
|
|
Yes |
|
(as applicable) |
|
|
|
|
Main Steam ( L&R ) |
Yes |
Yes |
|
|
First Stage |
|
Yes |
|
|
Extraction HP Turbine |
Yes |
Yes |
|
|
(as applicable ) |
|
|
|
|
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 5 |
OF 16 |
Measurement |
Temperature |
Pressure |
Flow |
Electric |
HPT Exhaust ( L&R) |
Yes |
Yes |
|
Power |
|
|
|||
Hot Reheat Steam ( L&R ) |
Yes |
Yes |
|
|
Extraction IP Turbine -I |
Yes |
Yes |
|
|
Extraction IP Turbine -II |
Yes |
Yes |
|
|
IP Turbine Exhaust ( L&R ) |
Yes |
Yes |
|
|
Condenser Back Pressure |
|
Yes |
|
|
Gross Generator Output |
|
|
|
Yes |
5.2Test Prerequisites
The test instruments required for the test must be assembled, installed and operability verified. If a problem is discovered with an individual instrument, the instrument will be repaired and calibrated before conducting the test.
5.2.1Instrument Installation
Instruments must be installed following good instrument practices. Reference the appropriate ASME Performance Test Code for each instrument type.
Pressure instruments which operate above atmospheric pressure require pressure-sensing lines to be blown down prior to installing the pressure instrument, and the instrument to be vented after pressurization.
5.2.2Pressure Measurement
Pressure sensing lines should be plumbed with a continuous downward slope from the pressure tap to the sensor to prevent pockets of steam or air.
The appropriate waterleg measurements for each pressure instrument should be made and entered as part of data for each instrument.
Instruments which operate below atmospheric pressure must be plumbed with a continuous upward slope from the pressure tap to the sensor to prevent the formation of pockets of condensate. A means to vent instruments which operate below atmospheric pressure prior to the start of each test run must be provided.
5.2.3Temperature Measurement
All thermowells should be cleaned and the bottoms polished prior to installing the temperature sensors. The RTDs should be installed in a manner to ensure good contact is made with the bottom well and secured
|
Centre For Power Efficiency And Environmental |
Procedure Number |
|
NTPC |
Protection, NOIDA |
CENPEEP/EFF/TP/301 |
|
|
|
|
|
|
TITLE |
Rev. 1/EMS |
|
CENPEEP |
Routine Turbine Efficiency Test |
Issue Date: 20/04/2000 |
|
|
Page: 6 |
OF 16 |
to ensure they are held firmly during use. Temperature sensor shafts which extend past the thermowells should be insulated.
5.3Test Instructions
Test runs must be conducted over the normal operating load range from Valves Wide Open (VWO) to Minimum Load.
5.3.1Units with Sequential Valve Control
Test runs must be conducted at the valve points.
5.3.2Units with Full Throttling Control
The operating range must be divided into equal increments based on the nominal load at
VWO (Valve Wide Open) and minimum.
5.3.3Exceptions to VWO (Valve Wide Open)
It may not be possible to achieve VWO with rated steam conditions on certain units. In this case, reducing the main steam pressure, and thereby increasing the steam specific volume, may allow VWO operation.
As an alternative, if VWO cannot be achieved with rated steam pressure, a lower valve point may be substituted for VWO on sequential valve controlled turbines. The travel of the control valve stem may be used on full throttling turbines.
5.3.4Operating Conditions for Each Test Run
5.3.4.1Unit Off Load Control and Steady
5.3.4.2Main Steam Pressure at Design Value
5.3.4.3Main Steam and Reheat Steam Temperatures at Current Expected Value
5.3.4.4Boiler Outlet O2 at Current Expected Value
5.3.4.5All Feedwater Heaters in Service, Normal Levels and Vent Settings, Normal Drain Routing