DETAILS OF DAILY WORKING
Date |
Day |
Hours worked |
Hours stopped |
Quantity load./disch. |
Remarks |
||
|
|
From |
to |
From |
to |
|
|
07.07.14 08.07.14 09.07.14
|
Mo Tu We
|
12 0 0 |
24 24 8
|
- - - |
- - - |
1250 2500 750 |
|
|
|
|
|
|
|
4500 |
|
Agents
|
TIME SHEET
|
|
Ship’s name m.s «Moskva»
|
Port Nikolaev |
|
Owners
|
Loading commenced Mo 07.07.14 1pm |
Loading completed We 09.07.14 8am |
Cargo Scrap |
Discharging commenced
|
Discharging completed |
Charter Party Gencon |
Cargo documents on board Th 10.07.14 10am |
Vessel sailed Th 10.07.14 12am |
Vessel arrived on roads Sa 05.07.14 8pm |
|
|
Vessel berthed Su 06.07.14 8am |
Bill of Lading quantity 4500 |
|
Notice of readiness tendered Mo 07.07.14 9am |
Laytime allowed for loading 1d 20h |
Laytime allowed for discharge |
Time to count from Mo 07.07.14 1pm |
Rate of demurrage |
Rate of despatch money |
LAYTIME COMPUTATION
Date
|
Day |
Time worked
|
Laytime used |
Time saved/on demurrage |
|||||
|
|
From
|
To |
days |
hours |
minutes |
days |
hours |
minutes |
07.07.14 08.07.14 09.07.14
|
Mo Tu We
|
12 0 0 |
24 24 8
|
- 1 - |
12 - 8 |
- - - |
|
|
|
Total: |
|
|
|
1 |
20 |
… |
… |
… |
… |
Agents
|
STATEMENT OF FACTS
|
|
Ship’s name m.s «Moskva»
|
Port Alexandria |
Notice of readiness tendered Tu 15.07.14 9am |
Owners
|
Bill of Lading quantity 4500 |
|
Cargo Scrap |
Loading commenced
|
Loading completed
|
Charter Party Gencon |
Discharging commenced Tu 15.07.14 1pm |
Discharging completed Fr 18.07.14 12am |
Vessel arrived on roads Mo 14.07.14 7pm |
Cargo documents on board
|
Vessel sailed Sa 19.07.14 1pm |
Vessel berthed Tu 15.07.14 7am |
DETAILS OF DAILY WORKING
Date |
Day |
Hours worked |
Hours stopped |
Quantity load./disch. |
Remarks |
||
|
|
From |
to |
From |
to |
|
|
15.07.14 16.07.14 17.07.14 18.07.14 |
Tu We Th Fr
|
12 0 0 0 |
24 24 24 12 |
- - - - |
- - - - |
750 1500 1500 750 |
|
|
|
|
|
|
|
4500 |
|
Agents
|
TIME SHEET
|
|
Ship’s name m.s «Moskva»
|
Port Alexandria |
|
Owners
|
Loading commenced
|
Loading completed
|
Cargo Scrap |
Discharging commenced Tu 15.07.14 1pm |
Discharging completed Fr 18.07.14 12am |
Charter Party Gencon |
Cargo documents on board
|
Vessel sailed Sa 19.07.14 1pm |
Vessel arrived on roads Mo 14.07.14 7pm |
|
|
Vessel berthed Tu 15.07.14 7am |
Bill of Lading quantity 4500 |
|
Notice of readiness tendered Tu 15.07.14 9am |
Laytime allowed for loading
|
Laytime allowed for discharge 3d |
Time to count from Tu 15.07.14 1pm |
Rate of demurrage |
Rate of despatch money |
LAYTIME COMPUTATION
Date
|
Day |
Time worked
|
Laytime used |
Time saved/on demurrage |
|||||
|
|
From
|
To |
days |
hours |
minutes |
days |
hours |
minutes |
15.07.14 16.07.14 17.07.14 18.07.14 |
Tu We Th Fr
|
12 0 0 0 |
24 24 24 12 |
- 1 1 -
|
12 - - 12
|
- - |
|
|
|
Total: |
|
|
|
3 |
|
… |
… |
… |
… |