ARKHANGELSK STATE TECHNICAL

UNIVERSITY

OFFSHORE FIELD DEVELOPMENT CONCEPTS

AND FACILITIES

OCT 2015

---------------

PART 6 :DEVELOPMENT PROJECT EXECUTION PHASE

--------------

Daniel Saincry

TABLE OF CONTENTS-PART 8:

PROJECT MANAGEMENT

GENERAL

CONTRACTUAL STRATEGY

PROJECT EXECUTION PLAN & PROJECT ORGANISATIONS

PLANNING

HSE

COST CONTROL

QUALITY CONTROL

2

INTRODUCTION

THE PROJECT’S MAGIC TRIANGLE

Quality means control of the process

and products

Quality

HSE means Health Safety and Environment Protection

 

HSE

 

+SS

Cost

Schedule

ns budget control

Schedule means forecast and,

ast

anticipation

 

3

THE PROJECT EXECUTION PLAN

A key « fundation » document

List what to do and how to do

Needs to be prepared at the very beginning of the basic engineering phase (first issue)

Constitutes the « road map » of the Project Team defining the objectives of the project

Is the first tool for the project team to communicate with the stakeholders of the project

Shareholders

State

Local authorities

4

PROJECT TEAM ORGANIZATION

1 – Factors to be considered

The technical characteristics of the project

The Owner’s background in project management – its own human resources in project management discipline

The project contractual strategy

The geographical location of the actors of the project during the various phases of the development

2 – – Organization principles

Organization and contractual strategy are deeply interdependent

The organization must evolve all along the main project phases as detailed hereafter.

The organization must suit the responsibilities of the actors of the project

(contractors, suppliers, company…)

The management and supervision team has to be located at the center of gravity of the activities.

5

TYPICAL PROJECT ORGANIZATION

6

PROJECT MANAGEMENT

7

PROJECT TEAM ORGANIZATION:

THE CAPACITIES OF THE PROJECT DIRECTOR

Leadership over the team members

Intellectually rigorous. No compromise with the truth

Ability to make the right decision at the right time.

Technically competent due to a wide work experience

Good common sense

Ability to communicate

Strong personality

Stress “resistant “ !

8

PROJECT ORGANIZATION

Project is specific, but the organization, in line with the Contractual Strategy must allow the Operator/Partners to keep control of the key aspects of the Project:

Schedule

Cost

Technical Quality

Safety, security, control of the environment.

The cost of the supervision is an important aspect but should not be the driving parameter.

The Project Organization must anticipate the operation and maintenance phases.

9