Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2015ARKH-P5-Field Development Evaluation(80s)

.pdf
Скачиваний:
10
Добавлен:
11.03.2016
Размер:
3.13 Mб
Скачать

LNG PLANT PROJECT LAY OUT

Plant lay out : surface

Pars LNG = 265 ha SPP11 = 125 ha

South Pars Phase 11 and Pars LNG meeting Tehran 21 Sept 2004

Land occupation = 315 ha

Reclaimed area

= 75 ha

Embankments

= 40 ha (incl)

1

 

31

OTHER TYPICAL PRE-PROJECT TECHNICAL (or not) STUDIES

Electrical

Control & ESD System

Telecommunication

Civil engineering

Structures

Pipelines and vessels

Mechanical

Corrosion

Surveys (surface & seafloor, bathymetry, geotechnical, …) requirements

Metering & Export systems

EBS (Environmental Baseline Study)

Preliminary EIS (Environmental Impact Assessment)

Sustainable development aspects, economical & social impact

32

CAPEX STRUCTURE

Main Equipment Bulk

Construction (onshore + offshore)

Transportation

Temporary Facilities

Construction camps

Engineering Services

Management & Supervision

Surveys

Insurance

Commissioning

Direct Costs + Indirect Costs = Technical Costs

Direct Costs

+

Indirect Costs

+

General

Expenses

+

Associated Expenses

+

Contingencies

=

Facilities Cost Estimate

33

COST ESTIMATION METHODOLOGY

34

PROJECT DEVELOPMENT

HOW TO PERFORM A COST ESTIMATE

THREE MAIN METHODS FOR COST ESTIMATING

First “the Rule of Thumb”: US$/bbl US$/MMcfd, or by analogy with an other project (ratio between capacity with exponent 0.6)

i.e. a project to produce 150 MMcfd (equivalent to 25 000 bbl/d) could cost 400MM US$, what about a 250 MMcfd project with similar conditions:

400 x 250/150 exp 0.6 = 543 MM US$

But of course we have to adjust by other factors: escalation, country…

Second method - “Semi-Analytic estimate” . Factorisation method is often used.

Finally the “Detailed Cost Estimate”,

35

EXAMPLE OF FACTORISATION METHOD

36

ACCURACY & CONTINGENCIES

Study type

Préliminary

Conceptual

Pre-project

Accuracy

+35 to 40%

 

+ 25 to 30 %

 

+15 to 20 %

 

 

 

 

 

 

 

Contingencies

25 to 30 %

15 to 20 %

10 to 15 %

37

PROJECT PLANNING

Example of level 1 project development planning

Level 1 - Schedule

 

2002

 

 

 

2003

 

 

2004

 

 

 

2005

 

 

 

2006

 

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

GENERAL

-Appraisal

-FEED Completion

-Contract Area & FDP

-3D Seismic Acquisition / Processing

OFFSHORE

-Tendering Cycle

-Wellhead Jackets

-Drilling

-Platforms

-Sea Lines

-Export Line & Receiving Facilities

ONSHORE

-Tendering Cycle

-Construction to 1st Gas

-Start-up – Stream 1

-Start-up – Stream 2

- DPSA - Commencement Date

01.10.06

38

PROJECT PREPARATION

&

DECISION TO DEVELOP

KEY ISSUES: PROJECT ECONOMICS EVALUATION

OBJECTIVES :

To have the monetary value of a project & to analyse the project value drivers

To compare technical alternatives

To evaluate tenders and to prepare negotiation positions

To forecast cashflows and to prepare budgets

To track on going project performances versus budget and forecast

Risks analysis, impact on project value & sensitivities

Reservoir uncertaintiesReserves ?

New technology

Costs ? Added value ?

‘’

‘’

Risks ? Production delay ?

Low oil prices

Project value

40

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]