Добавил:
Upload Опубликованный материал нарушает ваши авторские права? Сообщите нам.
Вуз: Предмет: Файл:

2015ARKH-P5-Field Development Evaluation(80s)

.pdf
Скачиваний:
10
Добавлен:
11.03.2016
Размер:
3.13 Mб
Скачать

PROJECT SANCTION :

KEY CHALLENGES

Geosciences aspects: Reservoir development plan, development phasing, possible upsides, reserves booking, reserves certification,

Technical: Production facilities selection, expected plant performances, site study, access to site, logistics, project schedule, innovations, use of associated gas…

Environmental: Environmental Baseline Study (EBS) & Environmental Impact Assessment (EIA), access to site, existing facilities or fabrication yards in the area,

Economics: cost estimate, OPEX, CAPEX, cost reduction analysis, market conditions, NPV (Net Present value), IRR (Internal Rate of

Return)…

Financing scheme: Project financing, banks loans, Partners financing, Credit Export Agencies loans..;

PROJECT SANCTION :

KEY CHALLENGES

Contractual: Contractual strategy selection, Local content, insurance scheme, constrained timing,

Legal: Taxation scheme, applicable laws and regulations, land acquisition or lease…

Social: Economical & social impact study, Local manpower availability, training programs,

Risk management: Risks analysis, market evolution, currency fluctuation, suppliers and contractor track records, security aspects…

PROJECT SANCTION :

KEY CHALLENGES

Host Government contract requirements

Fiscal terms

Associate gas requirements/flaring

Local content requirements Local market and skills

Training requirements:

Host country potential challenges

Local currency fluctuation

Local PIB growth

Security aspects

PROJECT SANCTION CHALLENGES:

KEY CRITERIA: PROJECT ECONOMICS EVALUATION

SANCTION PACKAGE is FORMALISED:

To have the monetary value of a project & to analyse the project value drivers (partners may have different target for Project IRR)

To compare technical alternatives

To forecast cashflows and to prepare budgets

To track on going project performances versus budget and forecast

To evaluate tenders and to prepare negotiation positions

Risks & sensitivities analysis

Risk analysis is performed to assess the impact of:

Reservoir uncertaintiesReserves ?

Tight market

Costs ? Added value ?

New technology

Costs ? Added value ?

‘’

‘’

Schedule? Production delay ?

Lower oil/gas prices

Project revenue

64

FIELD EVALUATION PROCESS – EXAMPLE

SOUTH PARS 2 & 3 DEVELOPMENT

CONCEPTUAL STUDIES: SOUTH PARS 2&3 PROJECT (1)

66

CONCEPTUAL STUDIES: SOUTH PARS 2&3 PROJECT (2)

SOUTH PARS (Iran) and NORTH FIELD (Qatar) are the largest nonassociated gas field in the world

SOUTH PARS characteristics

 

- Area

3,700 SQ KM

-

Gas in place

460 TCF

-

Condensate in place

17,100 MMBbl

Phases 2 & 3 characteristics

 

-

Gas Production

2,000 MMSCFD

-

Condensate Production

77,000 Bbl/d

-

Sulphur Production

500 t/d

67

CONCEPTUAL STUDIES: SOUTH PARS 2&3 PROJECT (3)

North Field general map

South Pars 2&3 wet scheme

 

RAS LAFFAN

1 BScfd

1 BScfd

 

0.9 BScfd

Qatargas I « dry scheme »

CONCEPTUAL STUDIES: SOUTH PARS 2&3 PROJECT (4)

General Principle

All possible technical solutions are envisaged

Best development scheme is selected

South Pars

Fluid transfer system from offshore: Mono phase or multiphase flow ?

Wet or Dry?

Constraints:

Viscosity

Pipe Corrosion due to the water Pipe length: 105 km

Studies result:

The multiphase WET scheme cost is lower (30% of Surface Facilities costs savings)

CONCEPTUAL STUDIES: SOUTH PARS 2&3 PROJECT (5)

COMMON FACILITIES: (DEVELOPED BY NIOC)

56” EXPORT LINE

SULPHUR HARBOUR CONDENSATE EXPORT SYSTEM

 

 

ONSHORE GAS TREATMENT PLANT

 

 

 

 

 

 

GAS LIQUID SEPARATION

 

 

 

 

 

 

4 PROCESS TRAIN

 

 

 

2 SUB SEA PIPELINES

 

 

2 BSCFD PROCESSING CAPACITY

 

 

 

 

 

 

 

 

32” AND 104 KM LONG

 

 

77,000 b/d CONDENSATE

 

 

 

 

 

 

 

 

WET SCHEME FOR RAW GAS

 

 

500 t/d SULPHUR

 

 

 

2 OFFSHORE PLATFORMS :

 

 

 

 

TRANSPORTATION

 

 

 

 

 

 

 

70 M. WATER DEPTH

 

 

 

 

 

 

 

41/2” PIGGY BACK LINE FOR MEG

NOT NORMALLY MANNED

 

 

 

 

 

 

 

TRANSPORTATION

 

 

 

 

 

 

 

MEG INJECTION OFFSHORE FOR

REMOTE FLARES

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CORROSION CONTROL

10 DEVELOPMENT WELLS EACH

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SPD3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SPD4

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Соседние файлы в предмете [НЕСОРТИРОВАННОЕ]